How to read a mine's annual technical report for production guidance
Where production guidance lives in an NI 43-101 technical report, and why the numbers on the page stop being the whole story once mining starts.

A technical report is a few hundred pages long and the production guidance you need sits in maybe four of them. Here's where to look and what the numbers mean once you find them.
Where the guidance number lives
Start with the mine plan section, usually filed under Mining Methods or Production Schedule depending on the author. Most NI 43-101 reports built under the 2011 CIM guidelines will give you a life-of-mine schedule as a table: tonnes mined, tonnes milled or processed, strip ratio, and ore grade, broken out by year. That table is the backbone of everything else in the report. The reserve estimate feeds it, the economic analysis runs off it, and the covenant language in a project loan is usually written against a version of it.
Don't stop at the summary table in the executive summary. It rounds numbers and sometimes blends ramp-up years in a way that flatters year one. The full schedule, further back in the document, will show you the annual tonnage the operator committed to on paper, including the slower early years most summaries smooth over.
Check the filing date before you lean on that schedule. A technical report gets filed when a specific trigger requires it: a reserve update, a financing, a change of control. The schedule inside it reflects conditions as they stood at that filing date, and it stays fixed on the page until the next trigger comes along. If the filing is three years old and there's been no material change disclosure since, the schedule reflects a mine plan that may have already been revised twice. Look for amendments or a newer NI 43-101 filed on SEDAR+ or EDGAR before you build a covenant test around a number that's gone stale.
Guidance versus what got moved
The technical report tells you what the operator planned to mine. It does not tell you what got mined. For that you're looking at quarterly MD&A, press releases, or whatever operational update the company puts out, and all three of those numbers come from the same source: the mine's own reconciliation of its own production. There's no third party in that chain unless the loan agreement specifically requires one.
That matters more in some years than others. A mine running ahead of its technical report schedule will say so loudly, usually in the first paragraph of a press release. A mine running behind tends to bury it in paragraph six, folded into language about "sequencing" or "grade variability." Reading the technical report guidance against the quarter's reported actuals is the only way to see that gap before it shows up in a covenant breach or a reserve writedown.
The reported actuals and the technical report guidance are both numbers the mine produced about itself. If you're a lender or an asset manager who needs a figure nobody on site generated, comparing company-reported tonnes against company-filed guidance doesn't get you there, no matter how carefully you read the report. That's the gap Pit Progression was built to close: an independent monthly volume read, built from the change in pit elevation between two survey dates, that you can set against the technical report's year-one or year-two schedule without waiting on the operator's own reconciliation.
A few things worth checking every time
Confirm whether the schedule is in dry tonnes or wet tonnes, and whether "mined" means ore only or ore plus waste. Mixing those up is the single most common way an outside reader overstates or understates how a mine is tracking. Also check which pit or phase the annual number refers to if the operation has more than one active cut. A multi-pit operation's company-wide guidance can mask one pit running well behind while another carries the total.
None of this tells you whether the mine is actually hitting the number it filed. For that you need a read that doesn't come from the mine. Pit Progression turns a month-over-month elevation difference into a moved-material figure you can check against the schedule yourself.